The Cabildo approves the project to improve the accessibility of the Barranco Seco, in San Sebastián
The objective is to improve accessibility to agricultural properties located in this area of El Molinito, which currently has difficulties in transit to the multiple plots found in this area.
The Cabildo of La Gomera has approved the project to improve the accessibility of the Barranco Seco, in El Molinito, with an investment of 2 million euros. The objective of this project is to promote the accessibility of the agricultural properties that are scattered in this area, through the execution of paved roads that access some lands from the GM-1 highway.
To achieve this, a runway of approximately 1,250 meters in length has been planned, with 5-meter sidings and a branch 250 meters long and 3.5 meters wide. Both ways, to promote your communication.
The works focus on earthmoving, demolition and restitution operations, including land clearing, trench excavation, demolition of the asphalt pavement, construction of masonry and concrete factories, removal of palm trees and demolition of enclosing walls of the affected lot.
Among the planned works of factory works, drainage and sanitation, the creation of retaining walls will be carried out, transversal drainage works will be carried out, concrete to protect pipes, execution of sanitation channels, with wells and corresponding connections. As for the pavements, a bituminous pavement and the corresponding irrigation will be placed, as well as a concrete pavement and placement of curbs.
This project seeks to improve the situation of annual surface runoff, which makes traffic difficult and prevents adequate access to the multiple plots that are located on the left bank of the ravine.