The insular Institution begins the works to provide solar panels in the buildings of the Hotel Escuela Rural Casa Los Herrera and cold storage rooms located in Vallehermoso
In addition, the installation of solar panels is planned for the energy supply of the interpretation centers Casa de la Miel de Palma and del Queso y el Pastoreo
The Cabildo of La Gomera is advancing in the implementation of renewable photovoltaic energy in different island buildings. This was reported by the president, Casimiro Curbelo, who stressed the determined commitment of the island Institution to materialize projects that allow achieving an energy model that makes La Gomera a cleaner, more efficient and sustainable island.
In this way, action has already begun at the Hotel Escuela Rural Casa de Los Herrera, which contemplates the placement of an individual self-consumption installation on a roof, provided with twenty 550W photovoltaic panels, with a peak power of 11.55 kW, and a generated energy generation of approximately 17,256.85 kWh/year. For this, the Cabildo has an investment of more than 38 thousand euros.
Added to this is that installation work has begun in the Vallehermoso cold chambers. For this, an installation is planned consisting of 96 photovoltaic panels of 460 Wp, grouped in seven strings, five with 14 panels and two with 13 modules. These strings are connected to two three-phase inverters of 17.5 kW nominal power each. The investment allocated to this action exceeds 39 thousand euros.
Progress is also being made in the materialization of the expansion of the photovoltaic capacity of the Socio-Health Center of San Sebastián de La Gomera, which foresees the placement of 95 photovoltaic modules with an installed power of 52.25 kW, connected to a 50 kW inverter. With this expansion, the center will reach a combined photovoltaic power of 100 kW, capable of generating approximately 147,692 kWh annually, thus covering a significant part of the electrical demand of the facilities without injecting surpluses into the network.
New photovoltaic installations in museum centers
The Cabildo also plans the installation of solar panels to supply energy to the interpretation centers Casa de la Miel de Palma, in Alojera, and del Queso y el Pastoreo, in Alajeró.
The Casa de la Miel Interpretation Center in Palma, one of the most visited centers in the island museum network, will have 33 modules with an installed power in panels of 14,025 kW and a 10 kW inverter. This facility, which is in the bidding phase, has a planned investment of more than 74 thousand euros.
On the other hand, in the Cheese and Grazing Interpretation Center, in Alajeró, the most recent on the island to open, the increase of the current photovoltaic generating field is projected, in order to reach the total self-consumption capacity, and with an estimated investment of 131 thousand euros. In this way, action will be taken on the current generation system of 36 panels, proceeding to clean it and electrically reconfigure it to improve its efficiency; and 36 more new panels will be added, which will be equivalent to a total installed power of 38.34 kWp (72 panels).