The close cooperation between the General Directorate of Coasts of the Government of the Canary Islands, the Cabildo of La Gomera and the City Council allows progress in the recovery of this connection of the municipality
The solution includes a crossing at a different level for vehicles and pedestrians over the ravine and the setback of the avenue to adapt the action to the protection conditions of the coastline.
The Valle Gran Rey City Council announces that the replacement and protection works of the section of Avenida Marítima and the mouth of the ravine will begin this Tuesday, after obtaining authorization from the General Directorate of Coasts and Management of the Canary Islands Maritime Space of the Government of the Canary Islands. The intervention will make it possible to recover the connection affected by the damage caused by Storm Therese and improve safety and mobility conditions in this environment.
The mayor of Valle Gran Rey, Borja Barroso, highlighted that "this progress is the result of close cooperation and coordination between the General Directorate of Coasts of the Government of the Canary Islands, the Cabildo of La Gomera and the City Council itself. The joint work has made it possible to achieve a technical solution that combines the recovery of the traffic of vehicles and people, the improvement of the drainage of the ravine and respect for the protection conditions of the coastline."
For his part, the president of the La Gomera Cabildo, Casimiro Curbelo, also highlighted the coordination between the administrations involved to advance the recovery of the infrastructure affected by Storm Therese. "From the first moment we worked together with the Government of the Canary Islands and the town councils to provide effective responses to incidents of extraordinary magnitude. In the case of Valle Gran Rey, this cooperation made it possible to advance a priority action to restore mobility and reinforce security in a particularly sensitive point of the municipality," he said.
One of the main elements of the action will be the execution of a step at a different level at the mouth. The water from the ravine will flow under the platform intended for vehicles and pedestrians, through ten drainage openings. This provision is designed to maintain the continuity of traffic also during the floods contemplated in the technical calculations, always within the expected safety conditions.
The action also contemplates the setback of the avenue inward, placing the drainage work under the road outside the maritime-terrestrial public domain. This adaptation responds to an essential condition of the Coastal authorization: avoiding the construction of fixed works within said public domain and making the recovery of mobility compatible with the protection of the coast.
"The solution will allow the water to have its passage space under the avenue and, above, we can maintain the connection for vehicles and people. We want to recover this road by incorporating improvements that reduce its vulnerability to new episodes of intense rain," explains Barroso.
In the island area, Curbelo recalled that the Cabildo had quantified the damage caused by this meteorological episode on the entire island at 42.7 million euros and that, since then, all available resources had been mobilized to accelerate recovery. In this sense, he specified that actions had already been awarded for an amount close to 20 million euros in the six municipalities. “This economic and technical effort was possible thanks to institutional cooperation and coordinated work between the different administrations, which made it possible to advance in the recovery of damaged infrastructure and incorporate solutions aimed at improving security and the capacity to respond to future adverse phenomena,” concludes the island president.
Temporary closure of pedestrian access
The City Council also informs that the provisionally enabled pedestrian crossing will be temporarily closed due to the work that is going to be carried out in the area. During this period, access to La Calera through this environment will be through the El Baluarte track, both for pedestrians and vehicles. The measure is necessary to guarantee safety during the execution of the works. The City Council appreciates the citizens' understanding and asks them to respect the signage and instructions of the responsible personnel.